Following the Chancellor’s Autumn Budget, the Government has announced that residential brownfield developments on sites of up to 1.5 hectares in England will be exempt from biodiversity net gain (BNG) requirements.
The intention is to reduce development costs and make it simpler to deliver homes on previously developed land.
For some schemes, this could ease a financial constraint. But how much difference could it make to your project, and what should you do now? David Ramsay, Head of Planning, and Gary Jeffries, Head of Residential Property, explore.
What has been announced?
BNG generally requires development in England, unless exempt, to deliver at least a 10% improvement in biodiversity.
This can involve creating or enhancing habitats on site, purchasing off-site biodiversity units or, as a last resort, buying statutory biodiversity credits.
However, in a drive to deliver more housing, the Budget introduced a further proposed exemption specifically for residential development on brownfield sites up to 1.5 hectares.
This is a targeted change, rather than an exemption for every brownfield development.
The commencement date and detailed eligibility rules are yet to be confirmed, so developers should not assume that the announcement immediately removes their existing obligations, but it could allow you to revisit previously unviable schemes to review them afresh with a view to potentially progressing once the new threshold is formally adopted.
What could BNG changes mean for developers?
Brownfield schemes can carry significant costs before construction begins, from demolition and remediation to infrastructure upgrades.
Where margins are already tight, additional requirements can affect whether a project if financially viable enough to proceed.
For schemes that qualify, the BNG exemption could reduce expenditure on habitat delivery, off-site units and associated management arrangements. It could also simplify part of the development process.
However, the potential saving will vary considerably, as David Ramsay, Head of Planning, explains:
“A scheme with substantial off-site biodiversity costs may see a greater benefit than one where BNG can already be delivered relatively easily.”