Since 27 January 2026, Ofgem’s authorisation conditions have brought new requirements for the organisations responsible for operating and supplying heat through relevant networks.
For landlords with shared heating systems in multi-let buildings or across estates, the implications extend into everyday property management.
Alongside maintaining the plant, owners and managing agents need to understand their responsibilities for charging, tenant communications, complaints and the continuity of heating services. The requirements that apply will depend on the network and the customers it serves.
With existing heat networks required to register with Ofgem by 26 January 2027, landlords need to establish whether their properties fall within scope now, who holds responsibility and whether their management arrangements meet the applicable rules.
Vail Williams’ Head of Property Asset Management, Carl Grint, explains what commercial landlords should review now, from identifying affected systems to preparing for registration and ongoing compliance.
Could your commercial property be affected?
Heat networks distribute heating, cooling or hot water from a central source. They can serve multiple buildings through a district network, or separate premises within a single building through a communal network.
This makes multi-let commercial properties with shared heating plant an important starting point for commercial landlords. Estates where a central system serves several buildings should also be reviewed. However, shared plant does not automatically mean a heat network needs to be registered. The system’s configuration, the premises it serves and the nature of the supply all matter.
For example, Ofgem has identified an exemption for communal networks that provide heating and cooling solely through air conditioning and do not supply hot water.
Industrial and self-supply networks also require separate consideration. These are within the regulatory framework but have fewer obligations than other network types.
Landlords therefore need to assess each heat system against Ofgem’s guidance, rather than assume that every shared installation is included or that commercial premises are excluded.
Who is responsible for the heat network?
One of the most important questions is which organisation holds the regulatory responsibility.
Ofgem distinguishes between two roles:
- The operator, which has control over and responsibility for the transfer of thermal energy through the network.
- The supplier, which is responsible for the contractual and customer-facing arrangements associated with supplying heating, cooling or hot water.
The same organisation can fulfil both roles or they can sit with different entities.
However, this distinction needs careful examination. A landlord may appoint a managing agent to administer charges and a contractor to maintain the plant, while retaining control over major investment and infrastructure decisions.
Appointing a contractor to carry out maintenance does not, by itself, transfer the operator’s regulatory responsibility.
Owners should therefore review the actual arrangements alongside leases, management agreements and maintenance contracts. Each party needs to understand its role, what information it holds and what it must do.
What needs to be ready for registration?
Existing relevant heat networks must be registered with Ofgem by 26 January 2027.
Completing the process requires information about the organisation and the individual network, including its technical characteristics, customers, metering, billing and relevant consumer protection arrangements.
Where the operator and supplier are different organisations, the operator starts the network registration and invites the supplier to complete the sections relevant to its role.
This creates a dependency, and therefore a compliance risk, since one party’s progress affects the other’s ability to finish.
For landlords with several properties, preparation might also involve bringing together information held by managing agents, engineering contractors, billing providers and previous managers. Starting the process early allows time to resolve missing records and clarify responsibilities.